Thursday, June 19, 2008

Plastering has started

Well we are now on day two of plastering finally! I have not posted for ages because plastering had been put off by an entire month to enable PD to fix the problems Kevin found at the pre-plaster inspection. From what I can tell it took a maximum of two days to actually fix the problems so the rest of the month was just messing around. Our site supervisor "A" obviously could not cope with the issues so he was taken off our job and we now have site supervisor "C". We are glad to be rid of "A" as he never called us once to let us know where we were up to.

In my last post on 28th May I emailed our CSR about the claimed rain days that it was not raining on and she was going to get back to me. Still no response, what a surprise! I have even emailed a reminder about it and since then forwarded the same email again. Maybe like our last CSR she has left the company and no-one has told us again???

Anyway it is great to see the plaster finally started apparently they will finish tomorrow or Monday and then a different crew come to do the skirtings etc.

This is the rumpus room half done.

This is our ensuite
This is the dining room, looking into the lounge room.

This is the most recent picture of the front of the house. It looks a lot neater now the bricks are clean.

Wednesday, May 28, 2008

Finally a Response

PD finally got back to us about some resolutions to the problems Kevin found.
- 2 of the issues have apparently been fixed (we have not been in the house lately so we will check this out tomorrow).
- 4 of the issues were explained how they are going to be fixed
- 5 of the issues are being discussed with the Construction Manager and remedial action will be determined and will be advised in due course

Monday, May 26, 2008

Frustration a plenty

Things are very frustrating at the moment. It has been nearly two weeks since PD has received Kevin's inspection report and we have had NO feedback! PD have had BSS back to check over the things in Kevin's report, I guess to decide whether to believe it but we have heard nothing about this either. Our site supervisor is not returning any of David's calls so we have no idea what is going on. Nothing has been done on the house over the last few days and even though we just paid the massive lockup invoice we still do not have a roof on our study so we are not even really at lockup.

Wednesday, May 21, 2008

Lockup we think?

It says in the Porter Davis 24x7 system that we are at lockup on 23rd May which is Friday but we just received the invoice today saying Congratulations! Your lockup stage is now complete??? As you can see from the pics it looks like we are at lockup. All the brickwork is finished and the doors are on but the little roof above those three windows you see in the front is not on yet (hence it rains inside the house).

It is very exciting to see the house starting to look like the display home. We have still heard nothing from our site supervisor in response to Kevin's Inspection and what they are going to do about the problems (it has been a week since they got the report). All we have heard from our CSR is that plastering is being put off until further notice. The lack of feedback is annoying.




This is our lovely front door that will be stained eventually. We are very happy with it.

The plaster has been delivered
The cornices have also been delivered, unfortunately they were left in this position in the entry as over the weekend it rained lots and the rain came in the study roof that has not been built yet and totally flooded the floor. The cornices are now laying in a pool of water. I'll just say they had better not use the bottom ones that have been laying in the water for days.

Tuesday, May 13, 2008

Bifold Doors In

Our bifold doors to the alfresco have been installed today. After many many clarifications with PD over the bifolds these are still not how we wanted them. We wanted the right hand door to be able to be opened as a separate door on its own but with this unit you have to open at least two doors like I have demonstrated. They still look really nice though, I will speak to admin about it but it is not a big deal.
Fully Open
We also had our independent inspector Kevin from New Homes Inspections (found him on the Homeone Forum) come to inspect the house today. There are quite a few issues to be rectified which will most certainly put plastering off. He will send me his report tomorrow.

Monday, May 12, 2008

Insulation

The wall insulation has been installed today and the frame has been straightened. The brickies are nowhere to be seen so lockup may still be a while off.



Friday, May 9, 2008

Jessie's girl

We were hoping for lockup today but the brickies were not there yesterday and are not there today either so it will not be happening today. The brickies have got around the entire house now but still have the top section to finish.



They have bricked right up to the roof on the right side of the house and a small section of the back.
The air conditioning an heating ducts were put in yesterday.
Why the title to this post you ask? When I got there today the sparkies were on site and the radio was on and one of the guys was singing Rick Springfield's Jessie's girl at the top of his voice. This was one of my favourite songs from the 80's so I thought it was great!
Here's a reminder if anyone needs one: http://www.youtube.com/watch?v=adaYUM5wl7c